1. Using new housing construction data as a predictor of construction equipment sales is an example of what type of forecasting method?
A) Causal B) Time series C) Judgement D) Market survey
2. Which of the following consequences is typical of a push-based supply chain?
A) Longer lead times B) Higher product obsolescence C) Lower economies of scale D) Smaller production batches
3. An item must be added to inventory to support new business. Which of the following inputs should be considered to determine minimum inventory level?
A) Consumption rate B) Qualified supplier C) ABC classification D) Number of sales transactions
4. Which of the following factors is a measure of supply chain reliability?
A) Order-fulfillment cycle time B) Perfect order fulfillment rate C) Upside supply chain flexibility D) Downside supply chain adaptability
5. Which of the following inputs is used in developing a project charter?
A) Business case B) Work breakdown structure C) Project management plan D) Proposed solutions