CompTIA PK0-004 Project + Certified Practice Exam Questions and answer - Part 12

1. The company has introduced a new online tool for managing performance, which allows functional and project managers to evaluate employees on the Internet. This action is called, which of the following?

A) internal reorganization
B) Change Business Processes
C) organizational changes
D) continuity planning
E) None


2. Which of the following documents should be used to provide reports on the high level of key stakeholders?

A) ~~ connection POS = Drop
B) None
C) project plan
D) dashboard
E) Technical task


3. Which of the following is the definition of the RFP?

A) The document sent to potential suppliers to obtain information on the qualifications and experience of the project.
B) The document sent to potential suppliers to request a proposal for the project.
C) The document sent to potential suppliers to request information, that information includes the price for the project.
D) The document sent to potential suppliers to request a commitment to the project
E) None


4. The client requested additional functions for active projects. Which of the following steps should be done next?

A) The changes requested in the BPC.
B) Updating all project documents.
C) None
D) To implement the required changes.
E) Assessing the impact of the changes.


5. The project is underway on the budget and the tasks on the critical path in the graph. Which of the following should the project manager do?

A) Release change request.
B) Review your plan.
C) Update the project management plan.
D) None
E) Impact Assessment Baseline


1. Right Answer: B
Explanation:

2. Right Answer: D
Explanation:

3. Right Answer: B
Explanation:

4. Right Answer: E
Explanation:

5. Right Answer: E
Explanation: