Inspirational journeys

Follow the stories of academics and their research expeditions

CompTIA PK0-004 Project + Certified Practice Exam Questions and answer - Part 19

Mary Smith

Sun, 19 Apr 2026

CompTIA PK0-004 Project + Certified Practice Exam Questions and answer - Part 19

1. The project team has acquired computers with warranties that extend through the entire project. Which of the following is used risk strategy?

A) share
B) Transfer
C) None
D) Avoid
E) soften


2. Which of the following chart is a graphical representation of the reasons for a particular case?

A) Common
B) Fishbone
C) None
D) Gantt
E) bar chart


3. Which of these roles have the authority to approve the financing of the project?

A) Chief Financial Officer (CFO)
B) Master
C) None
D) sponsor
E) Project Management Office (PMO)


4. Which of the following elements should be part of the assignment of responsibility matrix?

A) Resource manager, the consultant said,
B) None
C) Responsible, accountable, consulted, he informed
D) Responsible, accurate, confided,
E) Resource responsible, SIGNOFF, entrance


5. the Corporate Governance Committee has just approved a new project. Project Scheduler is currently developing a project schedule. Which of the following activities should be done in the first place?

A) Add maturities.
B) Adding resources.
C) None
D) Add information
E) Add start and end dates


1. Right Answer: E
Explanation:

2. Right Answer: B
Explanation:

3. Right Answer: D
Explanation:

4. Right Answer: C
Explanation:

5. Right Answer: D
Explanation:

0 Comments

Leave a comment