1. Right Answer: C
Explanation: The ALE of this project will be $ 108,000.Single Loss Expectancy is a term related to Quantitative Risk Assessment. It can be defined as the monetary value expected from the occurrence of a risk on an asset. It is mathematically expressed as follows:SLE = Asset value * Exposure factorTherefore,SLE = 200,000 * 0.45 -= $ 90,000As the loss is occurring once every month, therefore ARO is 12. Now ALE can be calculated as follows:ALE = SLE * ARO -= 90,000 * 12= $ 108,000
2. Right Answer: C
Explanation: Return On Investment (ROI) is a performance measure used to evaluate the efficiency of an investment or to compare the efficiency of a number of different investments. To calculate ROI, the benefit (return) of an investment is divided by the cost of the investment; the result is expressed as a percentage or a ratio.The return on investment formula:ROI = (Gain from investment - Cost of investment) / Cost of investmentIn the above formula 'gains from investment', refers to the proceeds obtained from selling the investment of interest.Incorrect Answers:A, B: These options are not related to the measurement of efficiency of an investment.D: RAID is described as a redundant array of inexpensive disks. It is a technology that allows computer users to achieve high levels of storage reliability from low- cost and less reliable PC-class disk-drive components, via the technique of arranging the devices into arrays for redundancy.
3. Right Answer: C
Explanation: Change requests must be documented to be considered. Alice should create a change request form and follow the procedures of the change control system.
4. Right Answer: D
Explanation: Availability relates to information being available when required by the business process in present as well as in future. Resilience is the ability to provide and maintain an acceptable level of service during disasters or when facing operational challenges. Hence they are most closely related.Incorrect Answers:A: Integrity relates to the accuracy and completeness of information as well as to its validity in accordance with business values and expectations. While the lack of system resilience can in some cases affect data integrity, resilience is more closely linked to the business information requirement of availability.B: Confidentiality deals with the protection of sensitive information from unauthorized disclosure. While the lack of system resilience can in some cases affect data confidentiality, resilience is more closely linked to the business information requirement of availability.C: Effectiveness deals with information being relevant and pertinent to the business process as well as being delivered in a timely, correct, consistent and usable manner. While the lack of system resilience can in some cases affect effectiveness, resilience is more closely linked to the business information requirement of availability.
5. Right Answer: D
Explanation: Approval of a project initiation document (PID) or a project request document (PRD) is the authorization for a project to begin.Incorrect Answers:A: Project management plan is being made after the project is being authorized.B: Risk response document comes under risk management process, hence the latter phase in project development process.C: Risk management document is being prepared later after the project initiation, during the risk management plan. It has no scope during project initialization.